6.3Order, dates and the Gantt chart

Available in:EnglishFrançais

Work in a project is placed across a timeline using dependencies, working calendars, and planned dates. You can structure how items relate to each other directly on work item pages or visually within the project views.

Dependencies and order

To establish dependencies between tasks, open a work item. The Waits for section lists the work items that must precede it and allows you to configure new links.

  1. Go to the work item page.
  2. Under Waits for, choose the preceding work item.
  3. Choose an option under How: Starts after it finishes, Starts when it starts, Finishes when it finishes, or Finishes when it starts.
  4. Enter a Lag in working days (a negative lag allows the work to start early).
  5. Add the dependency.

Only work items without sub-items can be linked. A work item with sub-items automatically takes its dates from those sub-items. A dependency that would result in a circular loop is refused, and the interface names the work items involved. When a work item is waiting for preceding work that has not yet finished, its Status shows Blocked.

A Deadline is a date the work must be completed by; it is distinct from the Due date. On the Gantt chart, a warning appears whenever the schedule exceeds the deadline.

When a work item waits for other tasks, its first dependency sets its Dates to follow what it waits for. It is scheduled to begin the working day after the last preceding item finishes (or later if a lag is defined), keeping its Duration. It automatically moves earlier or later whenever preceding items move. A work item without dates of its own acquires them through this link. If you choose to set dates by hand, the work item retains those manual dates and only shifts when explicitly adjusted; adding further dependencies does not override that choice. A work item waiting for nothing retains its dates as entered.

Cross-project dependencies

You can also link to tasks outside the current project:

  1. Under Waits for, select the search field to find work in another project from the projects you are permitted to open.
  2. Add the dependency.

The dates of that external item hold this project's work item back. However, the external work item can only be shifted within its own project and does not count toward this project's planned finish date. On the other project's work item page, your task is listed under Needed by.

Colleagues who do not have permission to open the external project will see only a note indicating work in a project they cannot open, without revealing its name. In the Dependencies view, the cross-project dependency appears as In another project. Any loop involving external projects is refused and named.

Planning methods

Above the Gantt chart, the Planning setting controls how project dates are scheduled:

  • From the start dates: Each work item begins where it is placed, and any dependent work follows.
  • Back from the due date (retro planning): Project managers choose Retro planning…, specify The project's due date, and select Show what moves. The system lists every work item that would shift along with its old and new dates. Nothing changes until you choose Apply.

When applying retro planning, every work item following the plan is scheduled as late as possible: the final items finish on The project's due date, while preceding tasks finish the working day before their dependent work requires them. Items previously set by hand will now follow the plan, new items take their place automatically, and finished or cancelled work keeps its dates. Changes to dependencies, durations, or the project due date update the plan immediately. If an item needs to have started in the past to meet the due date, the Gantt chart highlights it by name. Choose Plan from the start dates… to switch back to forward planning via the same review step.

The Gantt chart

The Gantt chart tab provides an interactive timeline of the project. It displays one bar per work item with its sub-items nested beneath it, milestones as diamonds, and internal bar shading that illustrates Completion from red (0 %) to green (100 %). Markers indicate Today and the Target date, while weekends and days off appear shaded.

  • Show by: Switch the view scale between Day, Week, Month, or Quarter.
  • Show the critical path: Highlights the chain of items that have no spare time. Any delay on these items delays the project finish past the Target date, or past the planned finish date if no target date is set. If the schedule exceeds the target, the interface marks it as After the target date.

Adjusting items on the chart

You can reposition items using mouse actions or keyboard controls:

  • Drag a bar horizontally to shift its dates, or drag its right edge to change its length.
  • Drag the circle at the end of a bar onto another bar to create a dependency.
  • With the keyboard, select a bar and press the arrow keys to move it by one day, hold Shift with an arrow key to resize it, or press Enter to open the work item.
  • Clicking the work item name in the left column opens the item page.

Date changes made directly on the chart are held until you confirm them. As you modify bars, an indicator above the chart shows how many items have uncommitted changes, accompanied by options to cancel or save the dates. Items waiting for the moved work are rescheduled only after saving. Cancelling discards held edits. If a date is rejected by the server, the bar remains in place with the reason displayed so you can adjust or cancel it.

Each bar uses the colour of its Status. Arrows indicate dependency status: green when the preceding item is done or cancelled, and red while it remains incomplete. Below the timeline, the legend details:

  • Waits for work that is done
  • Waits for work not done yet
  • Starts too early

Bmator only shifts dates automatically for work items set to follow what they wait for. If an item set by hand violates a dependency order, its connecting arrow becomes thick, red, and dashed, and an alert states how many dependencies are unfulfilled. Selecting Reschedule… lists each item that must move with its proposed dates; choosing Apply executes the moves.

Layout settings

The left column displaying names can be adjusted by dragging its divider, or folded away using the small arrow in its header to maximize timeline space. This column width is saved locally on your device. The timeline grid always stretches to fill the full width of the window, extending columns and shading past the latest tasks so that wider zoom levels (such as Month or Quarter) provide open space to drag items into.

Baselines

Project managers can use Take a baseline (with an optional name) to capture the current state of dates, durations, and Effort (hours). A project retains up to ten baselines.

  • The saved baseline appears as a thin grey bar beneath each work item.
  • Use Show the baseline to toggle its visibility.
  • An indicator reports whether the project finishes earlier or later than the saved reference.
  • The What moved since summary details which items changed finish dates and by how many days. Selecting an item opens it.
  • Baselines cannot be edited. You can create a new baseline, pick an earlier one using Compare with, or choose Delete it (which prompts for confirmation and leaves current dates untouched).

Exporting

Click Export to save an exact copy of the current schedule. Available formats include PDF for printing, PNG for presentation slides, and SVG for vector editing.

Roadmap and Dependencies views

Two companion tabs provide high-level and structural views of the schedule:

  • Roadmap: Designed for presenting to clients or executive boards, this tab shows only milestones and work items that have sub-items, arranged by month. Work cannot be dragged here; adjustments must be made on the Gantt chart or work item pages.
  • Dependencies: Displays linked work items as connected nodes and arrows, emphasizing The critical path in red. You can locate items with Find a work item, and clicking any node opens its work item page.