6.4Workload: who has how much work
The Workload tab displays who has how much work across the project, week by week. It provides an overview with one row per person who has work in the project and one column for each week.
Each cell indicates the person's hours of work for that week compared against the hours they give the project. The darker the cell, the fuller their week is scheduled. Cells displayed in red indicate that the person is over capacity. Weeks that include scheduled days off have reduced available capacity.
How hours are counted
Workload calculations determine cell totals using the following rules:
- When a Work item specifies an Effort (hours) value, that effort is shared among the people listed in Assigned to in proportion to their allocation. The shared hours are then spread across the working days scheduled for the item.
- When a work item has no effort specified, the calculation uses its Duration at the person's allocation.
- Work items marked finished or cancelled count nothing toward the workload.
- Work items that contain Sub-items count nothing directly; their individual sub-items count instead.
Work with no dates assigned is listed under each person's name as hours not scheduled.
Viewing and navigating workload details
- Select any week's cell to display a detailed list of the work items scheduled behind it, along with their associated hours.
- Select an individual work item from this list to open it.
- Use the arrow controls to navigate forward or backward to earlier or later weeks.
- Select This week to return immediately to the current calendar week.
- Use Weeks shown to adjust the total number of weeks displayed on the grid.
- Select Set capacities on People to navigate directly to the People page to update individual capacities.
Managing assignments and schedules
The Workload tab provides visibility only and never moves or reschedules items automatically. Reassigning work or adjusting planned dates remains entirely your decision.